This is my time plan for the project: ”Peace in Web 2.0”, which may be changed or updated in the future (in that case I will notify you). If there are any questions or if you have any feedback, don´t hesitate to e-mail me on edbertsson@gmail.com, or comment directly in this blog!
Pre-phase (June – September):
1st meeting with TFF
Specialization courses (15 hp) in Informatics at Umeå University ("Öppenhet på internet" and "Web 2.0: Begrepp, teknik och Innovation")
2nd meeting with TFF
Meeting with the TFF board
3rd meeting with TFF
Phase 1: Fieldwork preparation (18th -27th October)
- Start recruiting informants: When one or more webpages/portals have been selected, the recruiting process should be initiated as soon as possible.
Deliver revised Project Plan, time budget and status-report on 22th October
Phase 2: Fieldwork (28th October-12th November)
- Commence the netnography: This part includes the entree and participant observation in various social media, a number of qualitative interviews (preferably at least 5) online and in real life (irl) and, depending on time - an internet survey about usage and experiences of a social media platform.
- (Absence, 1st November) Lecturing in Örnsköldsvik for Youth Against Racism
- Continue the recruiting process
- Going trough written sources
- (Absence, 11-12th November) Participation at "Innovation In Mind 2010", http://www.innovationinmind.se/
Phase 3: Processing data (15-19 November)
- Selection of literature and sources: Which articles, webpages, books etc. should be included in the final presentation?
- (Absence 16th November) Participation at ”Jag bor i Malmö”-(A youth conference)
- Transcribing interviews
- Compiling surveys
Phase 4: Analysis ( 22 November – 8 December)
- Analyzing processed data
- Idea generating process
- Deliver status-report on 26th of November
Phase 5: Production and Visual Presentation (9-17 December)
- Producing action-plan (with suggestions) and a Visual presentation for the future ProPeace Platform
Final presentation: 17th December
Post-phase (2011):
- Follow-up meeting with TFF in January